侧卸式装载机,是靠铲斗将岩石铲起,用侧卸的方式将岩石装入矿车。由于活动范围比较大,掘进工作面空间比较狭窄,所以侧卸式装载机在工作和检修时容易引起挤伤人员,挤坏支架、电缆、设备等事故。为防止事故的发生,山东永保机械的有关工作人员提醒大家在操作侧卸式装载机的时候要注意一下几个方面:
1、机器工作前必须通知附近人员撤离,避免机器对人员造成挤碰;
Must notify nearby evacuation avoid impingement causing the machine to the staff before the machine work;
2、 操作中应经常检查电缆是否完好,避免压坏,避免与油管发生摩擦,引发火灾事故,应保证所有操作按钮完好;
Operation should always check that the cable is intact, avoid crushing avoid friction with the pipe, causing fires, should ensure that all action buttons intact;
3、 装岩前,应对岩堆洒水灭尘,无论没水或洒水装置损坏,都不能开机装岩;
Before the rock, the rock pile to deal with dust suppression sprinkler, whether or not water sprinkler damage, can not boot rock;
4、装载机上的照明装置一定要完好,使工作人员有一个良好的视线,避免挤伤人员的事故发生。同时良好的照明对提高生产效率也是非常有利的;
Lighting devices on the loader must be intact, so that staff have a good line of sight, to avoid the occurrence of accidents crushing people. Good lighting while improving production efficiency is very favorable;
5、 装载机工作和检修时,工作人员,特别是区(队) 长要注意掘进头的情况。发现有透水、冒顶、煤岩突出征兆时,应立即组织人员撤离到安全地方,并采取相应的措施;
When the loader work and maintenance staff, especially district (team) should pay attention to the situation long boring head. Found flooding, roof fall, when coal and rock prominent signs should organize personnel immediately evacuated to a safe place and take the appropriate measures;
6、当装载机举起铲斗时严禁人员在铲斗下方操作或进行检修。必须进行修理时,应有可靠的安全措施;
When the loader to lift the bucket at the bottom of the bucket is prohibited personnel operating or maintenance. When repairs must be carried out, should be a reliable safety measures;
7、 司机离开机器时必须切断电源。非机组操作人员不得擅自操纵机器,以免误操作而伤人。此外,检修结束后,等所有工作人员撤离机器周围后方可开机试车;
Drivers must cut off the power when you leave the machine. Non-crew operations personnel are not allowed to operate the machine, in order to avoid misuse and wounding. In addition, after the overhaul, such as the withdrawal of all staff around the machine before boot after trial;
8、不得用装载机进行调车。轨道的铺设,应保持装岩机最突出的部位,与岩帮之间的距离不小于500毫米。
Shall be adjusted by the loader vehicle. Laying tracks, rock loader should remain the most prominent position, and the distance between the rocks to help not less than 500 mm.